Project Timeline
№№ |
Activity |
Deadline | Deadline taking into account changes in educational process | Percentage |
Totally done (%) |
---|---|---|---|---|---|
1 |
Research of programming technologies used in semester project. Obtaining and analysis of individual assignment | September 30 |
November 10 |
5 |
5 |
2 |
Studying mathematical methods for solving a problem. Defining software requirements. Construction of use case diagrams, class diagrams and sequence diagrams. Development of algorithms for solving the problem. Design of XML schema. Test preparation | October 10 |
November 15 |
10 |
15 |
3 |
Software structure development. Implementation of the computational part of the software. Console test implementation |
October 31 |
November 25 |
40 |
55 |
4 |
Designing a graphical user interface. Implementation of graphical interpretation. Implementation of report generation tools. Build and debug a program |
November 20 |
November 30 |
20 |
75 |
5 |
Software testing |
November 25 |
December 5 |
5 |
80 |
6 |
Writing project paper and presentation |
December 15 | December 15 |
20 |
100 |
7 |
Semester project defence |
from December 15 |
from December 15 |
|
|